Students Parents Community Staff
About PAUSD
Adult School
Board of Education
Committees
Complaint Policies
Educational Partners
Employment
Fees
Measure A
Program Information
Addison ES
Barron Park ES
Duveneck ES
El Carmelo ES
Escondido ES
Fairmeadow ES
Hoover ES
Briones ES
Nixon ES
Ohlone ES
Palo Verde ES
Hays ES
Jordan MS
Stanford MS
Terman MS
Gunn HS
Palo Alto HS
District Information
Citizens' Oversight Committee
Opportunities / Outreach
Plannning and Design Meetings
Monthly Reports
Superintendent
Volunteer!
Youth Community Service
Palo Alto High School - New Performing Arts Center
Project Overview Project Plans
Project Schedule Meeting Minutes
Construction Updates

Project Overview

Paly's New Performing Arts Center is currently planned to have a seating capacity of 550-600 with approximately 400 at orchestra level and 200 at balcony level. A lobby with restrooms, tickets, concession and gallery display space will be incorporated, as well as a drama classroom with green rooms and adjacent changing rooms. Also provided will be a stage with side wings, a full fly, orchestra pit and trap room.

back to top

Project Plans

Project Schedule

Milestone Schedule Dates

Architect Contract Approval

April 14, 2009
Conceptual Design Approval June 22 , 2010
Schematic Design Approval January 17, 2012
Submit to DSA January 29, 2013*
Approval by DSA September 22, 2013*
Bid Opening November 22, 2013*
Award of Contract December 8, 2013*
Notice to Proceed December 18, 2013*
Substantial Completion June 13, 2015*
Planned Occupancy August 17, 2015*