Students Parents Community Staff
About PAUSD
Adult School
Board of Education
Committees
Complaint Policies
Educational Partners
Employment
Fees
Measure A
Program Information
Addison ES
Barron Park ES
Duveneck ES
El Carmelo ES
Escondido ES
Fairmeadow ES
Hoover ES
Briones ES
Nixon ES
Ohlone ES
Palo Verde ES
Hays ES
Jordan MS
Stanford MS
Terman MS
Gunn HS
Palo Alto HS
District Information
Citizens' Oversight Committee
Opportunities / Outreach
Plannning and Design Meetings
Monthly Reports
Superintendent
Volunteer!
Youth Community Service
Stanford Middle School
Project Overview Project Plans
Project Schedule Meeting Minutes
Construction Updates

Campus Profile

Stanford Middle School 480 E. Meadow Ave. Built in: 1953, 1955, 1965, 1972, 2003

Stanford Middle School is composed of ten single story buildings on the 26 acre campus. The campus is adjacent to both Hoover and Fairmeadow Elementary Schools, as well as Mitchell Park. The original buildings in 1953 included 3 classroom wings, the Admin, Library, Cafetorium, Gymnasium buildings and a shop building. An expansion of the campus included construction of a new classroom wing and an addition on the Library wing. A new math and science wing were constructed in 1972, along with expansions to the Admin, Library and Gym. Two further classrooms were added in 1972. During the Building for Excellence Program in 2001-2003, all buildings were modernized with new finishes, roofing, mechanical, electrical, and plumbing systems. The total renovation was done in lieu of replacement of the facility as planned in 1996.

back to top

Project Overview

The Stong Schools Bond project will remove the six existing portables and replace them with a new 2-story classroom building located near the industrial arts wing. The new 10 classroom building will increase capacity with 4 additional classrooms. Existing classrooms will receive a technology wall that consists of an interactive whiteboard and sound assist system, both that are proven to enhance student learning. Also, an improved drainage system will be installed allowing for the opportunity for improving the landscape campuswide.

back to top

Project Plans

Project Schedule

Milestone Schedule Dates

Architect Contract Approval

October 30, 2008
Conceptual Design Approval September 8 , 2009
Schematic Design Approval June 22, 2010 & September 28, 2010
Submit to DSA May 6, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2012
Award of Contract May 8, 2012
Notice to Proceed

May 30, 2012

Substantial Completion August 24, 2013*
Planned Occupancy January 1, 2014*

* Anticipated Dates - Subject to Change